Fire Fighting Design of Shanghai Metro Station

論文類型 技術與工程 發表日期 2001-05-01
來源 中國水網
作者 高乃云,Peng,Haiqing,Fan
關鍵詞 Subway station Fire Water Supply Subway fire fighting
摘要 The purpose of this article introduces characteristics of fire fighting design of Shanghai Metro Station, such as, the principles of fire fighting design, hydrant system, water screen system, sprinkler system, full automation and submerge chemicals system

出  自: CECS-TC24 and CCES-WWE-P United Annual Conference & Academic Exchange Between CP — IAPMO Technical Papers, May, 2001, Shanghai, p113-117.
發表時間: 2001-5

Gao Naiyun Peng Haiqing Fan Jinchu Deng yang
School of Environmental Science and Engineering,Tongji University,China
Add: 1239 Si Ping Rd.,Shanghai, Zip Code: 200092
Fax 021-65986786 Tel 021-65982691; 021-55057579

Abstract The purpose of this article introduces characteristics of fire fighting design of Shanghai Metro Station, such as, the principles of fire fighting design, hydrant system, water screen system, sprinkler system, full automation and submerge chemicals system, use of pipe material, meaning of leak current, measures of preventing it and otherwise in detail.

Keywords Subway station Fire Water Supply Subway fire fighting

A bid for design of Shanghai Metro Line One was invited in the summer of 1987. Then construction of Shanghai Metro reached a practical stage, including some works such as the feasible studies, etc. There are usually two floors in the subway station (the upper floor is the concourse and the blow one is the platform), which is as same as the stations of the other countries in the world. The station and the tunnel form a half - closed construction work. After the station put into operation, all kinds of electric equipment is serried and the passengers are crowded in the station. Once a fire disaster happens, the temperature in the tunnel will increase rapidly, the smoke becomes thicker and thicker, the passengers are too difficult to be evacuated, and fire fighters can‘t be easy to enter there for fire control. It will bring a great loss for the people‘s lives and property. Fire is the greatest disaster in the subway station according to the related reports. So fire-fighting design is viewed as a very vital work and fire control must be designed as an integrated system. There is no "Code for Subway Design " inland when Shanghai Metro Line One was in the stage of design. At that time, according to design experiences of subway stations in Beijing, Hongkong and foreign countries, it was decided that gas fire-extinguishing system was set in important equipment rooms of the station, such as the control center, the power distribution substation the communication equipment room and signals equipment room, etc. At the same time, it was decided that water screen system was set at the entrance of stair between the concourse and platform, hydrant system was in the other places, and sprinkler system was in concourse, which would be as a shop. But when designing stations in Shanghai Metro Line Two, the water screen system was canceled because of promulgation of new related codes and the others were same as Subway One‘s.

1Principles of Fire Fighting Design
· Fire fighting design of subway stations follows the principle — "Precaution must be the first, precaution and fire fighting must be integrated."
· Fire demand of water is decided according to one fire point at the same time along the subway.
· All water sources come from city water supply network and there are no reserved water source.
· Outlay of hydrants assures that, at the same time, two hydrants‘ water columns can reach wherever a fire happens.
· In the station, fire water pipes are detached from domestic water pipes and process water pipes so that fire water pipes are a independent and secure system.

2Fire Water Source

Fire water source directly comes from city water supply network without fire cisterns whether in Shanghai Metro Line One or Two. Fire pumping station is set up respectively in every subway station in order to reach fire pressure. Two-way service pipes should be considered in the design of subway station in principle; that is to say, two sources come from different city water supply pipes. But, in fact, there is only one water pipe can be as the source of fire water pumps near some subway stations. The pipe is usually a part of city ring pipeline. A valve is installed on the pipe and two service pipes come respectively from before and after the valve. Once there is something wrong with the source when a fire happens, close the valve and still guarantee one fire water source.

3Hydrant System

Basically, designs of the hydrant system are same between Shanghai Metro Line One and Two. Hydrant water supply is along all the line. The protected area of every station includes itself and a half line before and after itself. At the same time, a station is assured to supply fire water when there is something wrong with fire pumps of neighbor stations.Hydrant system fire flow is 20l /s. The flow of a squirt gun 5l /s. The shortest water column ≥ 10m . The space between fire hydrant boxes ≤ 50m in the concourse and ≤ 30m in the platform. The types of fire hydrant boxes in the Shanghai Metro Line Two are listed in table 1. Type Ⅲ fire hydrant boxes are mounted at entrances but not less than two entrances in every station. The hydrant boxes are used only as fire brigade inlets.

The Types of Fire Hydrant Chambers in the Subway Two table 1

Type Size (mm) Subassembly in the hydrant boxes place Ⅰ 1600x750x350 A hydrant of 65mm in diameter; a set of 19mm hose nozzle with a 25m-long hose; a set of hose reel of 25mm in diameter; a button for starting fire pump. Concourse of station; Where the length of a passage is longer than 25m. Ⅱ 1750x750x350 Two hydrants of 65mm in diameter; two sets of 19mm hose nozzle with a 25m-long hose; a set of hose reel of 25mm in diameter; a button for starting fire pump. platform Ⅲ 700x700x300 Two hydrants of 65mm in diameter without hose and hose nozzle Entrances of station

At the same time, the main pipes of hydrant system are arranged into ring pipeline. The ring pipeline in the concourse is along with the horizontal direction; the ring pipeline in the platform is along with the vertical direction. Pipes in the concourse are installed above false walls at both sides of it. Hydrant pipes in the platform of Shanghai Metro Line One are installed length ways below platform‘s boards; hydrant pipes in the platform of Shanghai Metro Line Two and The Second Phase Project of Rail Transit Pearl Line of Shanghai are fixed beside air tubes along with top boards. The diameter of the main pipe is 150mm in diameter and a valve is set at intervals of five hydrants.
Fire pumps are started or stopped by manual control in the pump station, started by button control in hydrant boxes (only started, but not stopped), are remotely controlled by station control room, and tele-monitored by fire center.
A fire main pipe is along every tunnel. Two parallel fire pipes in two tunnels between stations are connected with fire pipes in the stations by linking pipes in the station so that a ring pipeline takes place between stations and tunnels.
Two fire brigade inlets of 100mm in diameter put on above ground level (some on the wall) of the station. The municipal hydrants must exit between 15 - 40 meters away from the fire brigade inlet.
All the fire water supply pipes that go into or out of the station are considered to satisfy the demand of civil air defense.

4Water Screen System

Water screen system is only designed in Shanghai Metro Line One. It‘s at top of the stair and escalator between the concourse and the platform as a protection of separation. Once a fire happens, it separates the concourse and the platform, and prevents fire and smoke to enter into the concourse from the platform if the fire occurs in the platform and the reverse is also true.
Total water demand of water screen system is 60l /s.The water flow from nozzle of the most unfavorable point is ≥ 0.5l /s.m
The screen system adopts dry sprinkler system and type ZSY sprinkler valve, which made in China and by hand control or driving by alarm system. There is the room for sprinkler valve in every stair.
There are two water screen pumps and they are reserved each other. Water screen pumps draw water directly from city water supply pipes. Starting style of the pumps is by hand control through screen valve, is by hand control in the pump station, and remotely control from control room of the station or center room.
Water screen pipes form a ring at top of stair and escalator. A sprinkler head of the open system is made in China and installed at intervals of 1m along the three sides (the last side is closed because of the structure).
Four fire brigade inlets of 100mm in diameter are above ground level(some on the wall) with corresponding municipal hydrants.

5Fire Sprinkler System

The sprinkler system is placed in the underground market of concourse, which is built up at the same time with the subway. Sprinkler flow is 30l /s after calculation based on the formula of codes; the lowest pressure ≥ 50kPa; system operating time is 1 hour. There are two fire sprinkler pumps, one is in use, the other is reserved. The pumps draw water directly from city water supplies pipes. Sprinkler system consist of the control valve, ZSS wet alarm valve, the delay unit, the pressure switch, the water pressure alarm bell, the system test equipment, pressure meters, system drainage valves and pipes. Indication device of start/stop are in the control valve. Indicator of water flow are in the system. Automatic air valves are fixed on the top of main pipes. All of the sprinkler heads are closed, whose action temperature is 68 ℃ (red) . Sprinkler heads are fixed below air tubes and concrete installation places are corresponded with the figment in the station. Sprinkler systems are set in only some stations of Line One, but in all the stations of Line Two. In the design of The Second Phase Project of Rail Transit Pearl Line of Shanghai are fixed beside air tubes along with top, the place of the sprinkler pumps and related pipes are vacated in the majority of the stations. Sprinkler pumps can be controlled by alarm system or manual control inside the pump station, or can be remotely controlled by the control center.
Two fire brigade inlets of 100mm in diameter are placed on the ground of the station. The hydrants must exit between 15 and 40 meters away from the fire brigade inlets.

6Gas Fire Fighting System

1301 halogenated alkyl fire-extinguishing system is placed in Line One. After field survey and study, Inerge has been used in the design of Line Two. Inerge is in use in the design of The Second Phase Project of Rail Transit Pearl Line of Shanghai, too.
Full automation and submerge chemicals systems, consisting of automatic fire-extinguishing sprinkler equipment(the sprinkler system) and control-monitor equipment(control system), are set in the underground substation, center control room, the communication equipment room, the signal equipment room, the capacitor room, the high-low voltage distribution room, computer rooms and so on.
Because of absence of the code for full automation and submerge 1301 halogenated alkyl fire-extinguishing system in the course of design of Line One, the American related code (NFPA 12A -1980) was referred to. The complete set of American full automation and submerge 1301 fire-extinguishing system was expensively introduced into the subway.
Full automation and submerge chemicals system includes gas storage steel-containers, the container entrance valve, air jetting pipes and sprinkler heads. Control ways consist of automatic control, manual control and mechanical emergency control (semi-automation)
The place of fire extinguishers follows "Code for design and allocation of fire extinguishers in the building". Fire extinguishers are allocated based on "A" type of fire disaster in the middle-class danger.

7 Drainage of Wastewater from Fire Fighting

A wastewater cistern and a wastewater pump station are placed in every platform. The cistern volume and pump units are designed mostly according to drainage of fire water, besides seepage water from structure of the station. So the cistern volume and drainage capacity of pump units are above the total of fire water demand.

8 Prevention Electro-corrosion from Leakage of Current

One of duties in the subway station design is to prevent electro-corrosion from leakage of electricity in the subway station. What‘s leakage current? The subway train is driven by DC electric motor, which is supplied with 1500 v DC by a single trolley wire. The rails become back flow wires of drawing by electricity supply. As a result of electrical impedance in the rails, a voltage drop appears when drawing current enters the rails. A difference of electric pressure exists between the rails and the ground at the same time. So a leakage current appears between rails and underground structures and covered pipes. The current reaches near negative feedback point and enters rails again along underground structures and pipes. The leakage current is named as the leakage current. It can erode rails, their accessories, reinforcing steels of the underground structures and metal pipes. For prevention of erosion of fire water supply pipes and pump units, the fire water supply pipes link a 1-2meter-long insulator pipe (PVC-U pipe) which is 1.5m far away from the main structure body of station before fire water supply pipes enter into the concourse. The insulator pipes are in the place that is in dryness and easy for examination and repair. The pipes that cross the rail bed use plastic insulator pipes.
Rubber units of Insulate against vibration use as insulators for protection of pumps. A short insulator pipes are fixed in effluent pipe as an insulating way between pipe system and pump units.

9Pipe Materials

1) Fire water supply pipes(diameter ≤ DN100) adopt galvanizing steel pipes with screwed connection.
2) Fire water supply pipes(diameter > DN100) install seamless steel pipes with flange connection.

10Discussion and Suggestions

1) In design of Shanghai Metro Line One, water screen system is as a method of separation and protection at the top of stairs and escalators between the concourse and the platform. As experiments test, water screen can prevent the fire to spread and separate the concourse and the platform completely. At the same time, passengers search water for a feeling of security to be on fire psychologically so that they often hurried toward the entrance of stair with water. Obviously, the water screen system will help passengers to disperse and make passengers have the hopes of escaping with their life. So it‘s suggested that the water screen system should be set at the top of stairs and escalators between the concourse and the platform in the design of subway station.
2) There were no hose reels in the fire hydrant boxes in the design of Shanghai Metro Line One. It won‘t be disadvantage for the initial phase of fire fighting.
3) Sprinkler systems should be set not only in the concourse but also in the platform so that there is enough security for business development in the future in subway station. Though it‘s feasible that the room for prospective sprinkler pumps is left, it will be more difficult and more expensive to install these pipes in the future.

論文搜索

發表時間

月熱點論文

論文投稿

很多時候您的文章總是無緣變成鉛字。研究做到關鍵時,試驗有了起色時,是不是想和同行探討一下,工作中有了心得,您是不是很想與人分享,那么不要只是默默工作了,寫下來吧!投稿時,請以附件形式發至 paper@h2o-china.com ,請注明論文投稿。一旦采用,我們會為您增加100枚金幣。

成人福利视频在线观看_国产精品日韩久久久久_欧美全黄视频_欧美网色网址
亚洲高清在线视频| 天天爽夜夜爽夜夜爽精品视频| 中文字幕视频一区| 日韩黄色免费电影| 波多野结衣亚洲| 日韩视频一区二区在线观看| 国产精品久久久99| 另类中文字幕网| 日本电影亚洲天堂一区| 久久久精品tv| 日本亚洲最大的色成网站www| 91视频精品在这里| 久久久精品免费网站| 男人的天堂亚洲一区| 日本精品一级二级| 中文欧美字幕免费| 韩国精品在线观看| 欧美一级搡bbbb搡bbbb| 亚洲国产欧美日韩另类综合| 99久久综合精品| 国产午夜亚洲精品不卡| 麻豆精品久久久| 欧美区一区二区三区| 亚洲欧美日韩国产手机在线| 国产在线精品一区在线观看麻豆| 欧美久久久久久蜜桃| 亚洲男人都懂的| 成人18视频日本| 欧美激情一区二区三区全黄| 极品美女销魂一区二区三区免费| 91精品国产高清一区二区三区蜜臀| 亚洲午夜激情网页| 色哟哟一区二区| ㊣最新国产の精品bt伙计久久| 国产高清无密码一区二区三区| 精品久久久久久亚洲综合网| 美女免费视频一区二区| 欧美精品成人一区二区三区四区| 一区二区成人在线| 日本黄色一区二区| 最新中文字幕一区二区三区 | 日本视频一区二区三区| 欧美日韩中文一区| 一二三区精品视频| 色婷婷综合中文久久一本| 1000部国产精品成人观看| av资源网一区| 成人免费在线视频| 91小视频在线观看| 中文字幕在线观看不卡| av毛片久久久久**hd| 国产精品美女久久久久aⅴ国产馆 国产精品美女久久久久av爽李琼 国产精品美女久久久久高潮 | 精品粉嫩超白一线天av| 久久国产三级精品| 精品国偷自产国产一区| 久久er99热精品一区二区| 欧美大片在线观看| 极品少妇xxxx偷拍精品少妇| 久久一区二区三区四区| 国产精品综合二区| 国产欧美日韩在线视频| 成人午夜激情在线| 中文字幕制服丝袜一区二区三区| 91亚洲大成网污www| 一区二区三区四区蜜桃| 欧美三级在线看| 肉色丝袜一区二区| 欧美r级在线观看| 国产一区欧美日韩| 国产精品网曝门| 91蜜桃视频在线| 亚洲图片欧美一区| 91精品国产高清一区二区三区| 免费的成人av| 久久久久九九视频| 成人avav影音| 亚洲一区免费观看| 欧美一区二区大片| 国产精品香蕉一区二区三区| 国产精品久久久久久久久快鸭| 色综合一个色综合| 午夜欧美电影在线观看| 日韩三级电影网址| 国产成人免费视| 亚洲欧美一区二区三区极速播放 | 丝袜国产日韩另类美女| 日韩欧美一卡二卡| 国产成人精品免费在线| 亚洲另类色综合网站| 欧美日韩精品一二三区| 久国产精品韩国三级视频| 中文字幕av一区二区三区| 欧美午夜电影一区| 国内精品嫩模私拍在线| 国产精品的网站| 欧美日韩国产影片| 国产精品一卡二卡| 亚洲综合丝袜美腿| 日韩一级大片在线| 成人avav影音| 天天综合天天做天天综合| 2021中文字幕一区亚洲| 91视频观看视频| 日本免费在线视频不卡一不卡二| 国产网站一区二区| 欧美三级视频在线观看| 国产一区二区在线视频| 亚洲免费av在线| 欧美成人女星排名| 色婷婷综合久久久久中文一区二区| 日韩国产在线一| 国产精品久久久久aaaa樱花 | 精品三级在线观看| 91美女视频网站| 精品一区二区三区香蕉蜜桃| 亚洲人午夜精品天堂一二香蕉| 69堂亚洲精品首页| av不卡在线播放| 美女在线观看视频一区二区| 亚洲三级电影网站| 精品国产精品网麻豆系列| 日本精品视频一区二区三区| 国产精品一区二区无线| 亚洲成人中文在线| 欧美国产一区二区| 日韩一区二区在线看片| 91在线视频播放地址| 久久99久久久久| 亚洲综合区在线| 亚洲国产精品av| 91精品国产欧美一区二区成人 | 中文字幕+乱码+中文字幕一区| 91精品欧美久久久久久动漫 | 91欧美激情一区二区三区成人| 激情深爱一区二区| 五月激情六月综合| 日韩理论片在线| 久久精品一区二区三区av| 欧美另类久久久品| 91老司机福利 在线| 国产成人一区二区精品非洲| 秋霞影院一区二区| 亚洲精品第1页| 国产精品妹子av| 久久色.com| 日韩一区二区三免费高清| 色www精品视频在线观看| 福利电影一区二区三区| 极品少妇xxxx精品少妇| 日韩 欧美一区二区三区| 一区二区三区四区激情| 国产精品黄色在线观看| 久久这里只有精品6| 日韩一级二级三级| 555www色欧美视频| 欧美私模裸体表演在线观看| 91亚洲国产成人精品一区二三| 国产成人激情av| 激情成人午夜视频| 理论电影国产精品| 视频在线观看国产精品| 亚洲bt欧美bt精品| 亚洲狠狠爱一区二区三区| 亚洲精品国久久99热| 亚洲三级在线播放| 自拍偷拍亚洲激情| 国产精品二区一区二区aⅴ污介绍| 久久久久久99久久久精品网站| 精品日本一线二线三线不卡| 日韩一区二区三区在线观看| 欧美电影影音先锋| 欧美丰满嫩嫩电影| 337p亚洲精品色噜噜| 欧美顶级少妇做爰| 欧美妇女性影城| 5月丁香婷婷综合| 3d动漫精品啪啪| 欧美一二三四在线| 日韩女优制服丝袜电影| 欧美成人一级视频| 欧美tk—视频vk| 久久精品免视看| 欧美激情一区二区三区全黄| 中文字幕精品一区二区三区精品| 中文字幕精品三区| 国产精品大尺度| 伊人夜夜躁av伊人久久| 亚洲综合成人在线视频| 亚洲一区二区三区四区中文字幕| 亚洲一区二区三区四区五区黄| 亚洲国产综合视频在线观看| 五月天亚洲精品| 久久精品噜噜噜成人av农村| 经典三级在线一区| 国产精品原创巨作av| 播五月开心婷婷综合| 一本大道久久a久久精二百| 欧美综合欧美视频| 制服丝袜av成人在线看| 精品精品欲导航|